Initial Project Setup & Schedules
Build the master schedule once, carefully — this becomes the baseline every daily diary entry and progress calculation is measured against.
-
01Go to the Project screen and create a new project file to start.
-
02Go to Gantt to set up your Activities. Important: keep activities small and manageable — break each one down into no more than 5 sub-tasks for accurate tracking.
-
03Add Milestones in Gantt by adding them as an Activity with zero duration and zero quantity.
-
04Link Activities with dependencies to build your master schedule automatically — successor activities will shift on their own as predecessors change.
Do not change baseline activity start dates once you've begun capturing daily diaries. Data already tied to those dates — including recorded delays — will be lost.
Gantt Chart & Critical Path
The Gantt Chart shows your live project timeline. Use the Critical Path overlay to see exactly which activities are driving your completion date.
-
01Rotate your phone to landscape and tap the
Gantticon in the menu for the full timeline view. -
02Use the toggle switch — usually found at the top of the screen or in chart settings — to highlight the Critical Path in cyan.
-
03Activities on the critical path have zero slack. If any of them slip, the whole project slips with it — these are the activities to watch closest.
Tip: check the critical path view weekly, not just at project milestones — early slippage on a critical activity is far easier to recover from than late slippage.
Daily Diary & Weather
Capture daily site diaries to maintain a bulletproof, contract-ready record of every shift.
-
01Navigate to Diary and select the current date, or create a
New Entry. -
02Fetch Weather: tap the cloud icon or
Fetch Weatherbutton to automatically pull local conditions from Open‑Meteo. -
03Progress: record quantities installed for each activity and the progress of its sub-tasks. Use the edit icon on any activity card to enter data.
-
04Resources: assign the specific plant, labour, and materials used for that day's work.
Creating PDF Reports
Professional A4 site diaries and reports, ready to hand to clients, head office, or an auditor.
-
01On the Diary screen, look for the
PrintorExporticon. -
02The app generates a compact PDF report optimised specifically for A4 printing.
-
03Reports include weather, progress logs, resource usage, and any site instructions, RFIs, and delays recorded for the period.
Data Backup & Recovery
Your site records live locally on your device first — back them up so a lost or replaced phone never means lost project history.
-
01Go to the Data screen (Data Management).
-
02Sign in with your Google Account.
-
03Tap
Backupto upload your entire project database to your own Google Drive app sandbox. -
04If you change phones, use
Restoreon the new device to pull your data back down.
Your backup is stored in your own Google Drive account, under your own Google sign-in — not on a third-party server.